Completed comprehensive spec-driven documentation: - SPEC.md (222 lines): Project scope, objectives, constraints - ARCHITECTURE.md (290 lines): System design, components, data flow - REQUIREMENTS.md (168 lines): Functional & non-functional requirements - API_SPEC.md (556 lines): 15 API endpoints with schemas - SECURITY.md (188 lines): STRIDE threat model, security controls - ROADMAP.md (203 lines): 5 phases, 8 milestones, risk register Total: 1,627 lines of specification documentation Milestone M1 complete - Ready for Phase 0 (Rust scaffolding)
This commit is contained in:
244
ROADMAP.md
244
ROADMAP.md
@ -1,57 +1,203 @@
|
||||
# Linux_Patch_API - Development Roadmap
|
||||
|
||||
## Project Timeline Overview
|
||||
|
||||
**Start Date:** 2026-04-09
|
||||
**Target Production:** 2026-07-17
|
||||
**Total Duration:** 14 weeks (Aggressive timeline)
|
||||
**Phase Strategy:** Sequential (no overlap)
|
||||
|
||||
---
|
||||
|
||||
## Project Phases
|
||||
|
||||
### Phase 1: Foundation
|
||||
**Target Date:** [TBD]
|
||||
**Status:** Not Started
|
||||
### Phase 0: Rust Project Scaffolding
|
||||
**Duration:** 3 days
|
||||
**Target Date:** 2026-04-09 to 2026-04-12
|
||||
**Status:** Ready to Start
|
||||
|
||||
- [ ] Complete all specification documents
|
||||
- [ ] Set up development environment
|
||||
- [ ] Initialize git repository
|
||||
- [ ] Configure CI/CD pipeline
|
||||
- [ ] Establish security baseline
|
||||
|
||||
### Phase 2: Core API Development
|
||||
**Target Date:** [TBD]
|
||||
**Status:** Not Started
|
||||
|
||||
- [ ] Implement authentication system
|
||||
- [ ] Build patch management endpoints
|
||||
- [ ] Build software management endpoints
|
||||
- [ ] Implement audit logging
|
||||
- [ ] Unit test coverage >80%
|
||||
|
||||
### Phase 3: Security Hardening
|
||||
**Target Date:** [TBD]
|
||||
**Status:** Not Started
|
||||
|
||||
- [ ] Penetration testing
|
||||
- [ ] Security audit
|
||||
- [ ] Implement rate limiting
|
||||
- [ ] Complete threat model validation
|
||||
- [ ] Compliance review
|
||||
|
||||
### Phase 4: Production Readiness
|
||||
**Target Date:** [TBD]
|
||||
**Status:** Not Started
|
||||
|
||||
- [ ] Performance optimization
|
||||
- [ ] Documentation completion
|
||||
- [ ] Deployment automation
|
||||
- [ ] Monitoring and alerting
|
||||
- [ ] User acceptance testing
|
||||
|
||||
## Milestones
|
||||
| Milestone | Description | Target Date |
|
||||
|-----------|-------------|-------------|
|
||||
| M1 | Spec completion | [TBD] |
|
||||
| M2 | Alpha release | [TBD] |
|
||||
| M3 | Beta release | [TBD] |
|
||||
| M4 | Production release | [TBD] |
|
||||
|
||||
## Risk Register
|
||||
[List identified risks and mitigation strategies]
|
||||
- [ ] Initialize Rust project with Cargo
|
||||
- [ ] Set up project structure (src/, tests/, configs/)
|
||||
- [ ] Configure Cargo.toml with dependencies (actix-web, tokio, openssl, serde, etc.)
|
||||
- [ ] Set up Clippy and rustfmt for code quality
|
||||
- [ ] Create initial module structure (api, auth, jobs, packages, config, logging)
|
||||
- [ ] Configure .gitignore for Rust projects
|
||||
- [ ] Set up initial logging framework
|
||||
|
||||
---
|
||||
|
||||
### Phase 1: Foundation
|
||||
**Duration:** 2 weeks
|
||||
**Target Date:** 2026-04-12 to 2026-04-26
|
||||
**Status:** Not Started
|
||||
|
||||
- [ ] Complete all specification documents ✅ (in progress)
|
||||
- [ ] Set up development environment (Rust toolchain, IDE config)
|
||||
- [ ] Initialize git repository ✅ (complete)
|
||||
- [ ] Configure CI/CD pipeline (GitHub Actions or GitLab CI)
|
||||
- [ ] Establish security baseline (dependency scanning, cargo-audit)
|
||||
- [ ] Set up test framework (cargo test, integration test structure)
|
||||
- [ ] Create systemd service file template
|
||||
- [ ] Set up internal CA infrastructure for mTLS certs
|
||||
|
||||
---
|
||||
|
||||
### Phase 2: Core API Development
|
||||
**Duration:** 6 weeks
|
||||
**Target Date:** 2026-04-26 to 2026-06-07
|
||||
**Status:** Not Started
|
||||
|
||||
- [ ] Implement mTLS authentication layer
|
||||
- [ ] Implement IP whitelist enforcement
|
||||
- [ ] Build configuration management (YAML loading, validation, auto-reload)
|
||||
- [ ] Build job manager (queue, status tracking, WebSocket broadcast)
|
||||
- [ ] Implement Package Management endpoints:
|
||||
- GET /api/v1/packages (list/filter/sort)
|
||||
- GET /api/v1/packages/{name} (details)
|
||||
- POST /api/v1/packages (install)
|
||||
- PUT /api/v1/packages/{name} (update)
|
||||
- DELETE /api/v1/packages/{name} (remove)
|
||||
- [ ] Implement Patch Management endpoints:
|
||||
- GET /api/v1/patches (list available)
|
||||
- POST /api/v1/patches/apply (apply patches)
|
||||
- [ ] Implement System endpoints:
|
||||
- GET /api/v1/system/info
|
||||
- GET /api/v1/health
|
||||
- POST /api/v1/system/reboot
|
||||
- [ ] Implement Job Management endpoints:
|
||||
- GET /api/v1/jobs (list)
|
||||
- GET /api/v1/jobs/{id} (status)
|
||||
- POST /api/v1/jobs/{id}/rollback
|
||||
- [ ] Implement WebSocket streaming (/api/v1/ws/jobs)
|
||||
- [ ] Implement audit logging (systemd journal + file fallback)
|
||||
- [ ] Unit test coverage >95%
|
||||
- [ ] Integration tests for all endpoints
|
||||
|
||||
---
|
||||
|
||||
### Phase 3: Security Hardening
|
||||
**Duration:** 3 weeks
|
||||
**Target Date:** 2026-06-07 to 2026-06-28
|
||||
**Status:** Not Started
|
||||
|
||||
- [ ] Penetration testing (internal/external)
|
||||
- [ ] Threat model validation (verify all STRIDE mitigations)
|
||||
- [ ] Security control implementation review
|
||||
- [ ] Fuzz testing on API endpoints
|
||||
- [ ] Certificate validation testing
|
||||
- [ ] Config file tampering resistance testing
|
||||
- [ ] Privilege escalation testing
|
||||
- [ ] Fix all security findings
|
||||
- [ ] Security documentation completion
|
||||
|
||||
---
|
||||
|
||||
### Phase 4: Production Readiness
|
||||
**Duration:** 3 weeks
|
||||
**Target Date:** 2026-06-28 to 2026-07-17
|
||||
**Status:** Not Started
|
||||
|
||||
- [ ] Performance optimization (benchmarking, profiling)
|
||||
- [ ] Documentation completion (README, deployment guide, API docs)
|
||||
- [ ] Deployment automation (package creation: .deb, .rpm)
|
||||
- [ ] Installation script development
|
||||
- [ ] User acceptance testing
|
||||
- [ ] Final security review
|
||||
- [ ] Production deployment checklist
|
||||
- [ ] Release v1.0.0
|
||||
|
||||
---
|
||||
|
||||
## Milestones
|
||||
|
||||
| Milestone | Description | Target Date | Status |
|
||||
|-----------|-------------|-------------|--------|
|
||||
| M0 | Phase 0 complete (scaffolding) | 2026-04-12 | ⏳ Pending |
|
||||
| M1 | All spec documents complete | 2026-04-09 | ✅ Complete |
|
||||
| M2 | Development environment ready | 2026-04-15 | ⏳ Pending |
|
||||
| M3 | CI/CD pipeline operational | 2026-04-22 | ⏳ Pending |
|
||||
| M4 | mTLS + IP whitelist working | 2026-05-03 | ⏳ Pending |
|
||||
| M5 | Core API functional (Alpha) | 2026-06-07 | ⏳ Pending |
|
||||
| M6 | Security testing complete (Beta) | 2026-06-28 | ⏳ Pending |
|
||||
| M7 | Production release (v1.0.0) | 2026-07-17 | ⏳ Pending |
|
||||
|
||||
---
|
||||
|
||||
## Risk Register
|
||||
|
||||
| ID | Risk | Likelihood | Impact | Mitigation Strategy | Owner |
|
||||
|----|------|------------|--------|---------------------|-------|
|
||||
| R001 | Rust learning curve delays development | Medium | Medium | Pair programming, Rust documentation, community support | Dev Team |
|
||||
| R002 | mTLS certificate management complexity | Medium | High | Early CA setup, detailed documentation, testing certs | Security |
|
||||
| R003 | Package manager API differences across distros | High | Medium | Pluggable backend architecture, extensive testing per distro | Dev Team |
|
||||
| R004 | Security vulnerabilities in dependencies | Low | High | cargo-audit in CI, regular dependency updates, minimal deps | Security |
|
||||
| R005 | Performance issues with concurrent jobs | Medium | Medium | Load testing in Phase 3, configurable concurrency limits | Dev Team |
|
||||
| R006 | Scope creep during development | Medium | High | Strict spec adherence, change control process | PM |
|
||||
| R007 | Internal CA infrastructure delays | Low | High | Start CA setup in Phase 0, use test certs for development | Security |
|
||||
| R008 | systemd integration issues | Low | Medium | Early systemd testing, reference existing Rust systemd services | Dev Team |
|
||||
|
||||
---
|
||||
|
||||
## Resource Requirements
|
||||
|
||||
### Development Team
|
||||
| Role | Count | Commitment |
|
||||
|------|-------|------------|
|
||||
| Rust Developer | 1-2 | Full-time |
|
||||
| Security Engineer | 1 | Part-time (Phases 1, 3, 4) |
|
||||
| QA/Test Engineer | 1 | Part-time (Phases 2, 3, 4) |
|
||||
|
||||
### Infrastructure
|
||||
| Resource | Purpose | Notes |
|
||||
|----------|---------|-------|
|
||||
| Development Server | Code development | Ubuntu 22.04 LTS |
|
||||
| Test Servers | Multi-distro testing | Ubuntu, Debian, RHEL, Alpine, Arch |
|
||||
| CI/CD Runner | Automated testing | GitHub Actions or self-hosted |
|
||||
| Internal CA | Certificate issuance | Separate secure host |
|
||||
|
||||
### Tools & Services
|
||||
| Tool | Purpose | Cost |
|
||||
|------|---------|------|
|
||||
| Rust Toolchain | Development | Free |
|
||||
| cargo-audit | Security scanning | Free |
|
||||
| Git/Gitea | Version control | Self-hosted |
|
||||
| Wireshark | Network analysis | Free |
|
||||
| Burp Suite | Security testing | Community (Free) |
|
||||
|
||||
---
|
||||
|
||||
## Success Criteria
|
||||
|
||||
### Phase 0 Success
|
||||
- [ ] Cargo project builds without errors
|
||||
- [ ] All dependencies resolved
|
||||
- [ ] Code quality tools configured and passing
|
||||
|
||||
### Phase 1 Success
|
||||
- [ ] CI/CD pipeline runs on every commit
|
||||
- [ ] Test framework operational with >95% coverage target
|
||||
- [ ] Internal CA operational with test certificates
|
||||
|
||||
### Phase 2 Success
|
||||
- [ ] All 15 API endpoints functional
|
||||
- [ ] mTLS authentication working
|
||||
- [ ] IP whitelist enforced
|
||||
- [ ] WebSocket streaming operational
|
||||
- [ ] Audit logging complete
|
||||
- [ ] Unit test coverage >95%
|
||||
|
||||
### Phase 3 Success
|
||||
- [ ] Penetration testing complete with all critical findings resolved
|
||||
- [ ] Threat model validated
|
||||
- [ ] Security documentation complete
|
||||
|
||||
### Phase 4 Success
|
||||
- [ ] Performance benchmarks met
|
||||
- [ ] Documentation complete
|
||||
- [ ] Package builds (.deb, .rpm) successful
|
||||
- [ ] UAT sign-off received
|
||||
- [ ] v1.0.0 released
|
||||
|
||||
---
|
||||
|
||||
*Following kiro spec-driven development standards*
|
||||
|
||||