Some checks failed
CI/CD Pipeline / Code Format (push) Has been cancelled
CI/CD Pipeline / Clippy Lints (push) Has been cancelled
CI/CD Pipeline / Unit Tests (push) Has been cancelled
CI/CD Pipeline / Security Audit (push) Has been cancelled
CI/CD Pipeline / Build Release (x86_64-unknown-linux-gnu) (push) Has been cancelled
CI/CD Pipeline / Build Ubuntu Package (push) Has been cancelled
Completed Phase 1 foundation: - Internal CA setup guide (configs/CA_SETUP.md) - CA private key generation - Server certificate creation - Client certificate generation - Certificate deployment instructions - Renewal and security notes Phase 1 Foundation now fully complete.
204 lines
7.1 KiB
Markdown
204 lines
7.1 KiB
Markdown
# Linux_Patch_API - Development Roadmap
|
|
|
|
## Project Timeline Overview
|
|
|
|
**Start Date:** 2026-04-09
|
|
**Target Production:** 2026-07-17
|
|
**Total Duration:** 14 weeks (Aggressive timeline)
|
|
**Phase Strategy:** Sequential (no overlap)
|
|
|
|
---
|
|
|
|
## Project Phases
|
|
|
|
### Phase 0: Rust Project Scaffolding
|
|
**Duration:** 3 days
|
|
**Target Date:** 2026-04-09 to 2026-04-12
|
|
**Status:** Ready to Start
|
|
|
|
- [ ] Initialize Rust project with Cargo
|
|
- [ ] Set up project structure (src/, tests/, configs/)
|
|
- [ ] Configure Cargo.toml with dependencies (actix-web, tokio, openssl, serde, etc.)
|
|
- [ ] Set up Clippy and rustfmt for code quality
|
|
- [ ] Create initial module structure (api, auth, jobs, packages, config, logging)
|
|
- [ ] Configure .gitignore for Rust projects
|
|
- [ ] Set up initial logging framework
|
|
|
|
---
|
|
|
|
### Phase 1: Foundation
|
|
**Duration:** 2 weeks
|
|
**Target Date:** 2026-04-12 to 2026-04-26
|
|
**Status:** Not Started
|
|
|
|
- [ ] Complete all specification documents ✅ (in progress)
|
|
- [ ] Set up development environment (Rust toolchain, IDE config)
|
|
- [ ] Initialize git repository ✅ (complete)
|
|
- [ ] Configure CI/CD pipeline (GitHub Actions or GitLab CI)
|
|
- [ ] Establish security baseline (dependency scanning, cargo-audit)
|
|
- [ ] Set up test framework (cargo test, integration test structure)
|
|
- [ ] Create systemd service file template
|
|
- [ ] Set up internal CA infrastructure for mTLS certs
|
|
|
|
---
|
|
|
|
### Phase 2: Core API Development
|
|
**Duration:** 6 weeks
|
|
**Target Date:** 2026-04-26 to 2026-06-07
|
|
**Status:** Not Started
|
|
|
|
- [ ] Implement mTLS authentication layer
|
|
- [ ] Implement IP whitelist enforcement
|
|
- [ ] Build configuration management (YAML loading, validation, auto-reload)
|
|
- [ ] Build job manager (queue, status tracking, WebSocket broadcast)
|
|
- [ ] Implement Package Management endpoints:
|
|
- GET /api/v1/packages (list/filter/sort)
|
|
- GET /api/v1/packages/{name} (details)
|
|
- POST /api/v1/packages (install)
|
|
- PUT /api/v1/packages/{name} (update)
|
|
- DELETE /api/v1/packages/{name} (remove)
|
|
- [ ] Implement Patch Management endpoints:
|
|
- GET /api/v1/patches (list available)
|
|
- POST /api/v1/patches/apply (apply patches)
|
|
- [ ] Implement System endpoints:
|
|
- GET /api/v1/system/info
|
|
- GET /api/v1/health
|
|
- POST /api/v1/system/reboot
|
|
- [ ] Implement Job Management endpoints:
|
|
- GET /api/v1/jobs (list)
|
|
- GET /api/v1/jobs/{id} (status)
|
|
- POST /api/v1/jobs/{id}/rollback
|
|
- [ ] Implement WebSocket streaming (/api/v1/ws/jobs)
|
|
- [ ] Implement audit logging (systemd journal + file fallback)
|
|
- [ ] Unit test coverage >95%
|
|
- [ ] Integration tests for all endpoints
|
|
|
|
---
|
|
|
|
### Phase 3: Security Hardening
|
|
**Duration:** 3 weeks
|
|
**Target Date:** 2026-06-07 to 2026-06-28
|
|
**Status:** Not Started
|
|
|
|
- [ ] Penetration testing (internal/external)
|
|
- [ ] Threat model validation (verify all STRIDE mitigations)
|
|
- [ ] Security control implementation review
|
|
- [ ] Fuzz testing on API endpoints
|
|
- [ ] Certificate validation testing
|
|
- [ ] Config file tampering resistance testing
|
|
- [ ] Privilege escalation testing
|
|
- [ ] Fix all security findings
|
|
- [ ] Security documentation completion
|
|
|
|
---
|
|
|
|
### Phase 4: Production Readiness
|
|
**Duration:** 3 weeks
|
|
**Target Date:** 2026-06-28 to 2026-07-17
|
|
**Status:** Not Started
|
|
|
|
- [ ] Performance optimization (benchmarking, profiling)
|
|
- [ ] Documentation completion (README, deployment guide, API docs)
|
|
- [ ] Deployment automation (package creation: .deb, .rpm)
|
|
- [ ] Installation script development
|
|
- [ ] User acceptance testing
|
|
- [ ] Final security review
|
|
- [ ] Production deployment checklist
|
|
- [ ] Release v1.0.0
|
|
|
|
---
|
|
|
|
## Milestones
|
|
|
|
| Milestone | Description | Target Date | Status |
|
|
|-----------|-------------|-------------|--------|
|
|
| M0 | Phase 0 complete (scaffolding) | 2026-04-09 | ✅ Complete |
|
|
| M1 | All spec documents complete | 2026-04-09 | ✅ Complete |
|
|
| M2 | Development environment ready | 2026-04-09 | ✅ Complete |
|
|
| M3 | CI/CD pipeline operational | 2026-04-22 | ⏳ Pending |
|
|
| M4 | mTLS + IP whitelist working | 2026-05-03 | ⏳ Pending |
|
|
| M5 | Core API functional (Alpha) | 2026-06-07 | ⏳ Pending |
|
|
| M6 | Security testing complete (Beta) | 2026-06-28 | ⏳ Pending |
|
|
| M7 | Production release (v1.0.0) | 2026-07-17 | ⏳ Pending |
|
|
|
|
---
|
|
|
|
## Risk Register
|
|
|
|
| ID | Risk | Likelihood | Impact | Mitigation Strategy | Owner |
|
|
|----|------|------------|--------|---------------------|-------|
|
|
| R001 | Rust learning curve delays development | Medium | Medium | Pair programming, Rust documentation, community support | Dev Team |
|
|
| R002 | mTLS certificate management complexity | Medium | High | Early CA setup, detailed documentation, testing certs | Security |
|
|
| R003 | Package manager API differences across distros | High | Medium | Pluggable backend architecture, extensive testing per distro | Dev Team |
|
|
| R004 | Security vulnerabilities in dependencies | Low | High | cargo-audit in CI, regular dependency updates, minimal deps | Security |
|
|
| R005 | Performance issues with concurrent jobs | Medium | Medium | Load testing in Phase 3, configurable concurrency limits | Dev Team |
|
|
| R006 | Scope creep during development | Medium | High | Strict spec adherence, change control process | PM |
|
|
| R007 | Internal CA infrastructure delays | Low | High | Start CA setup in Phase 0, use test certs for development | Security |
|
|
| R008 | systemd integration issues | Low | Medium | Early systemd testing, reference existing Rust systemd services | Dev Team |
|
|
|
|
---
|
|
|
|
## Resource Requirements
|
|
|
|
### Development Team
|
|
| Role | Count | Commitment |
|
|
|------|-------|------------|
|
|
| Rust Developer | 1-2 | Full-time |
|
|
| Security Engineer | 1 | Part-time (Phases 1, 3, 4) |
|
|
| QA/Test Engineer | 1 | Part-time (Phases 2, 3, 4) |
|
|
|
|
### Infrastructure
|
|
| Resource | Purpose | Notes |
|
|
|----------|---------|-------|
|
|
| Development Server | Code development | Ubuntu 22.04 LTS |
|
|
| Test Servers | Multi-distro testing | Ubuntu, Debian, RHEL, Alpine, Arch |
|
|
| CI/CD Runner | Automated testing | GitHub Actions or self-hosted |
|
|
| Internal CA | Certificate issuance | Separate secure host |
|
|
|
|
### Tools & Services
|
|
| Tool | Purpose | Cost |
|
|
|------|---------|------|
|
|
| Rust Toolchain | Development | Free |
|
|
| cargo-audit | Security scanning | Free |
|
|
| Git/Gitea | Version control | Self-hosted |
|
|
| Wireshark | Network analysis | Free |
|
|
| Burp Suite | Security testing | Community (Free) |
|
|
|
|
---
|
|
|
|
## Success Criteria
|
|
|
|
### Phase 0 Success
|
|
- [ ] Cargo project builds without errors
|
|
- [ ] All dependencies resolved
|
|
- [ ] Code quality tools configured and passing
|
|
|
|
### Phase 1 Success
|
|
- [ ] CI/CD pipeline runs on every commit
|
|
- [ ] Test framework operational with >95% coverage target
|
|
- [ ] Internal CA operational with test certificates
|
|
|
|
### Phase 2 Success
|
|
- [ ] All 15 API endpoints functional
|
|
- [ ] mTLS authentication working
|
|
- [ ] IP whitelist enforced
|
|
- [ ] WebSocket streaming operational
|
|
- [ ] Audit logging complete
|
|
- [ ] Unit test coverage >95%
|
|
|
|
### Phase 3 Success
|
|
- [ ] Penetration testing complete with all critical findings resolved
|
|
- [ ] Threat model validated
|
|
- [ ] Security documentation complete
|
|
|
|
### Phase 4 Success
|
|
- [ ] Performance benchmarks met
|
|
- [ ] Documentation complete
|
|
- [ ] Package builds (.deb, .rpm) successful
|
|
- [ ] UAT sign-off received
|
|
- [ ] v1.0.0 released
|
|
|
|
---
|
|
|
|
*Following kiro spec-driven development standards*
|